7/607 Interchange


Frequently Asked Questions


How is this project funded?
This project is funded through the 2006 Bond Referendum.

How long is construction going to take?
The expected completion date is December 2010.

What will happen to the Lexington Drive intersection and signal?
The existing signal will be modified with this project, however, the signal and intersection must remain in place. This is the only access for Smith Circle residents and businesses until one of the following occurs:
A. Connection to Riverside Parkway towards Howards Hughes to the west.
B. Construction of the Lexington flyover bridge over Route 7.