Project Schedule
December 2008 - Contract Awarded - COMPLETED
January 2009 - Begin Construction - COMPLETED
July 2009 - Begin Night Closures for Bridge Work - COMPLETED
October 2009 - Divert Route 607 Traffic onto Temporary Pavement - COMPLETED
April 2010 - Shift Traffic onto Bridge
Open Western Ramps to Traffic
Detour Remaining Traffic Movements [Stage 2 Detour Map] - COMPLETED
August 2010 - Open Eastern Ramps to Traffic - SCHEDULED AUGUST 25TH WEATHER PERMITTING
September 2010 - Close George Washington/Richfield Intersection - SCHEDULED SEPTEMBER 1ST WEATHER PERMITTING
December 2010 - Complete Construction of Route 7 & Route 607 Interchange